When does a new project require a new substation or transmission connection?

Primary Category

Grid & Transmission

Question Type

Technical

Tags

Grid; Transmission; Substations; Grid Connection

Short Answer

A new substation or transmission-level connection is required when an existing distribution connection cannot safely accommodate the project, lacks the necessary physical facilities, or would require more extensive modification than a new connection arrangement. Project size is important, but the decision ultimately depends on the PSS, network configuration, available substation space and the Grid Owner’s approved connection scheme.

Why This Matters

A new substation, switching station or transmission interconnector can add substantial cost, land requirements and development time. Developers therefore need to determine the likely connection architecture before finalising the site, plant capacity, delivery date or bid price.

What We Know

A project is more likely to require major new infrastructure when:

For distribution-connected LSS, the 2024 guideline sets indicative TNB connection ranges:

These are connection categories, not automatic entitlements. The actual capacity remains subject to network conditions and the PSS. Distribution-connected LSS must connect at an existing Distribution Licensee-owned substation under the current guideline. Energy Commission: LSS Connection Guideline

For transmission-connected LSS, Malaysia’s guideline describes two principal arrangements:

1. Connection to an existing substation. This is possible if the substation has space to extend its busbars, install a complete connection bay and accommodate the required protection and control panels.

2. Connection to an existing transmission line. If connection is made by looping into a nearby overhead line or underground cable, the developer must construct a new switching station or TNB Interconnection Facility to the Grid Owner’s specifications.

Transmission-connected LSS generally means connection at 132 kV or above and capacity of at least 30 MWac, unless the Energy Commission approves otherwise. The PSS and the Grid Owner/System Operator determine the appropriate voltage, injection capacity and scheme.

The infrastructure may include:

What We Don't Know

Connected Questions

People & Organisations

Sources

HELP BUILD THE ANSWER

What would you add to this answer?

Have a useful source, first-hand experience or a different interpretation? Help us strengthen this brief by sharing evidence, filling a gap or suggesting a correction.

Join the investigation

What question should we investigate next?

Economists, engineers, developers, investors, researchers, regulators and energy users see different parts of the transition. Tell us what you think deserves investigation.

Submit a question
WHY THESE QUESTIONS MATTER

Where could the next opportunity emerge?

Questions create opportunity. Understanding where the energy transition is heading helps reveal the technologies, projects, capital and expertise that will be needed next.

01

Technology

The solutions that turn open questions into deployable answers — from storage chemistries to grid intelligence.

02

Projects

The pipeline of solar farms, substations and interconnections waiting to be built and financed.

03

Capital

Where investment flows next as the transition reshapes risk, return and the shape of the market.

04

Expertise

The engineers, economists and regulators whose knowledge decides how fast the answers arrive.